Project Status
Date | Description |
1/24/2014 |
Begin loading of data in to test system of GradesFirst |
1/16/2014 |
Interface between GradesFirst and UA is under development. |
12/6/2013 |
GradesFirst representatives were on site to conduct a Discovery/Needs Assessment with UA representatives. The GradesFirst representatives will use the information gathered in these sessions to customize a solution based on the needs of UA. |
10/30/2013 |
Presentation was made to executive Steering Committee. Gained Steering Committee approval to move forward with implementation. |